Commissioning/Startup Services

Contract period

October 2019-May 2020

 

Location

Corpus Christi, Texas, USA

 

Challenge

Quality Companies was to deliver commissioning/startup, along with the installation of all equipment, structures and materials required to complete the telecommunications systems onsite at the Corpus Christi Liquefaction Project Stage 2.

 

Work scope

Site Acceptance Testing was performed, along with supply, fabrication and transport of permanent equipment, structures and equipment. The work scope included equipment setup and establishing all required temporary facilities to support the work. Telecommunication components such as Wireless Access Points (WAPs), PAGA and speakers were assembled and associated equipment and materials were mechanically completed.